News

January 2026

14 January 2026

Current status

  • Pre-consultation with Lake Simcoe Region Conservation Authority (LSRCA) is complete.
  • Detailed evaluation of several design alternatives has been completed, and a preferred design approach has been selected.
  • The recommended design approach is to construct an armourstone retaining wall with boulder toe protection, with all work occurring entirely on Town-owned shoreline property.
  • 60% detailed design is now complete.

Next Steps

  • Contact residents who will be affected by the work to discuss the project.
  • Finalize detailed design including the tender-ready package and obtain all required permits for construction.
  • Complete procurement and award a construction contract (late spring/early summer 2026).
  • Complete construction of the revetment during the late summer/fall 2026.