News

September 2024

19 September 2024

The engineering design stage of the High Street improvement project has recently begun.

The following briefly summarizes key aspects of the project:

Background

  • The objectives of the project include:
    • Beautify and enhance the commercial attractiveness of High Street in downtown Sutton’s Business Improvement Area (BIA) with streetscaping improvements including:
      • Multi-use path, configuration of parking and sidewalks to enhance boulevard use and pedestrian access
      • Street furniture, street trees, street lighting
      • Consideration of potential additional options (if feasible) such as:
        • Creation of a multi-purpose zone that can be used for parking and local “pop-up” events
        • Relocation of overhead hydro
        • A community entrance feature to High Street from Highway 48
    • Upgrade and modernize the local road, stormwater and water supply infrastructure.
  • In late August 2024 CIMA+ was awarded the engineering assignment for the project.
  • The main elements of the design phase of the engineering assignment include investigations, preliminary design, stakeholder communications, detailed design and tendering.
    • Once the primary design concepts are determined in the preliminary design step, a Business Disruption Mitigation Plan will be developed for discussion in stakeholder meetings that are to be implemented as part of the communications plan (see below).

Current status

  • The project kick-off meeting with the consultant, CIMA+, was held on Sept. 5, 2024.
  • Work has begun on the following tasks:
    • Background information collection and review
    • Development of a draft stakeholder communications plan addressing:
      • Creation and posting of project-related information and regular updates to a Town-hosted project website and social media.
      • Conducting a number of focused meetings/design workshops with stakeholder groups.
        • These workshops will review key design concepts and solicit stakeholder feedback before moving to the next step in the design process.
      • Distribution of letters/notices to affected local residents at key project milestones.
    • Compilation of information required to support the detailed design

Next steps

  • Completion and roll out of the stakeholder communication plan including:
  • Field investigations are planned to start in the latter part of September and will include:
    • Surveying
    • Identification and clearance of all underground utilities
    • Geotechnical drilling investigations