Construction look-ahead: Week of July 27, 2026

July 24, 2026

  • Bridge contractor, Clearwater Structures, will begin mobilizing onto the High Street bridge.
    • The contractor will set up on site for construction work activities.
    • Partial asphalt removals will begin.
  • General contractor, CRCE, will continue work along High Street from Hawkins Street to West Street, installing the above-ground temporary watermain.
    • The contractor will hand-deliver 72-hour water disruption notices to affected residences when they anticipate switching water supply from the underground watermain to the temporary line.

High Street downtown detour map

Map of local detour for High Street Reconstruction project. Northbound traffic is rerouted from River Street to Queen Street to Black River Road. Southbound traffic is rerouted from West Street to North Street until Burke Street.

Construction bypass detour map

Map of construction bypass detours. Vehicles travelling west/south along Highway 48 can take Park Road to Black River Road to Dalton Road. Vehicles travelling north/east on Highway 48 can take Old Homestead Road to McCowan Road to Baseline Road to Dalton