Overview
Drainage improvement measures are being carried out along Station Road from Old Homestead Road to Pefferlaw Road. This will include new curbs and sidewalks from Old Homestead Road to Hubbard Street, and isolated improvements from Hubbard Street to Pefferlaw Road.
At the same time, a new multi-use pathway (MUP) will be constructed
along Old Homestead Road from Forestry Drive to Station Road to increase safety for
pedestrians and cyclists. Several safety measures were incorporated into the MUP
design including speed humps, increased signage and a new pedestrian crosswalk.
Background
- Concerns have been raised by residents and Town staff due to frequent ponding of water and accumulation of loose gravel and sand on the sidewalk and edge of the pavement along a portion of Station Road. These conditions pose safety concerns and increase maintenance efforts.
- There is also an opportunity to improve the pedestrian and cyclist connection between Station Road, the pedestrian bridge on the Pefferlaw River and the Woodlands subdivision with access to York Regional trails. Creation of this connection will enhance pedestrian and cyclist safety while supporting additional active transportation in Georgina.
- The objectives of the project include design and construction of:
- The necessary drainage improvements along Station Road
- A multi-use pathway or sidewalk along a portion of Old Homestead Road
- In October 2024, Chisholm Fleming and Associates was awarded the engineering assignment for the project.
- In October 2025, the Regional Municipality of York
transferred ownership of Old Homestead Road to the Town of Georgina, from
Weirs Sideroad to Station Road.
- The main elements of the design phase of the engineering assignment include investigations, preliminary design, detailed design and tendering.
- Chisholm Fleming and Associates will also carry out the
inspection and contract administration during the construction phase.
Project updates
Current status
- Detailed design is complete, with the final review underway.
- The construction phase is targeted for spring 2026 and is expected to be completed by fall 2026.
Next steps
- Permits
- Tendering for construction
- Construction commencement
Current status
- The project kick-off meeting took place on Nov. 6, 2024
- The following tasks are currently complete:
- Background review of available data
- Site investigations and surveying
- Residents fronting the projects limits have received notifications
- Preliminary design
- The following tasks are currently underway:
- Detailed design
Next steps
- Permits
- Tendering
- Construction is targeted to begin in summer 2025
The engineering design stage of the Station Road Drainage Improvements Project has recently begun. The following briefly describes key aspects of the project:
Current status
- The project kick-off meeting took place on Nov. 6, 2024
- The following tasks are currently underway:
- Background review of available data
- Site investigations and surveying
- Residents fronting the projects limits have received notifications
Next steps
- Complete preliminary design
- Detailed design
- Tendering
- Construction is targeted to begin in spring/summer 2025
Questions
Have a question?
Submit your question to Georgina's team
To ask a question you must create an account or log in.
These are the people that are listening and responding to your questions.
Adam LaCroix
Project Manager, Capital Projects
{{question.description}}