September 2025

26 September 2025

Current status

  • Construction for the Golfview Crescent watermain replacement will begin the week of Sept. 8, 2025. The work will take approximately two weeks to complete.
  • Once the Golfview Crescent watermain replacement has been completed, the Road Repair program will begin work in the general area on repaving the entire Golfview Crescent.
  • Queensway South watermain (Joe Dales Drive to Miami Drive) construction drawings have been completed.

Next steps

  • Queensway South watermain project construction to start in spring 2026 pending Council budget approval for 2026.