The Lake Drive multi-use pathway (MUP) marked its first year of implementation along Lake Drive in 2025. The following briefly describes key aspects of the project:

Current status

  • The MUP was fully implemented June 27, 2025
  • The MUP was fully removed October 2, 2025
  • Permanent features were installed along Lake Drive including:
    • Sidewalk extension
    • Speed hump installation
    • New full-stop intersections
    • Improved intersection turning movements
    • Dedicated pedestrian sidewalks
    • New guiderail and hand rails
    • Line painting
    • Signage
  • MUP features that will be seasonally implemented:
    • Flexible bollard placements
    • Modular traffic island at Lake Drive and South Drive
    • Traffic signage (NO LEFT TURNS, DO NOT ENTER, etc.)
    • Pedestrian signage (SHARE THE PATH, educational awareness, etc.)

Next steps

  • A Council Report detailing traffic and pedestrian data, budgetary impacts, feedback received, construction / implementation updates, and continuous improvement will be presented by end of year 2025.
  • MUP implementation in 2026; dates to be confirmed.